Defence Vote Group
|
|
Summary
of Committee's proposals
|
|
2002 REV
|
|
|
902.92
|
|
|
Gross ELS figure for Vote Group
|
|
905.53
|
|
|
Gross Pre-Budget target (PBT) for Vote Group
|
|
884.16
|
|
|
Savings below ELS required to reach Pre-Budget
target (share of €900m)
|
21.37
|
|
|
Gross savings proposed by the Committee to
contribute to €900m target
|
41.76
|
|
|
Proposed Revised Gross Allocation (as per Table
1)
|
|
863.77
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
€m
|
€m
|
|
|
Estimate bid submitted by the Defence Vote
Group (in line with pre-Budget target)
|
884.16
|
2003
Proposed Allocation for each subhead
|
|
| |
|
|
|
|
|
Plus additional pressures which
Committee accepts must be met:
|
|
|
|
| |
Fishery Protection }
|
|
|
|
| |
Management Information Framework }
|
5.00
|
|
|
| |
Total additions
|
5.00
|
|
|
| |
|
|
|
|
| |
Estimates bid including pressures
|
889.16
|
|
|
| |
|
|
|
|
|
Less savings proposed
by the Committee
|
|
|
|
|
Subhead
|
|
|
|
|
|
A
|
Administrative Budget efficiency dividend
|
0.39
|
19.14
|
|
|
B
|
Permanent Defence Forces pay - further slowdown
in recruitment
|
3.00
|
374.03
|
|
|
G
|
Defensive equipment (postpone 2nd phase of Armoured
Personnel Carrier programme)
|
7.00
|
40.22
|
|
|
H
|
Aircraft - reduce spend on training aircraft
by 50%
|
9.00
|
31.52
|
|
|
L / V
|
Building / Barrack re-investment (E)
|
6.00
|
29.60
|
|
| |
Total savings
|
25.39
|
|
|
| |
|
|
|
|
| |
Proposed Revised Gross Allocation
|
863.77
|
|
|
| |
|
|
|
|
| |
(E) refers to Estimating Savings
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|